Refusal to Submit Cost or Pricing Data
Arizona Administrative Code
Arizona Administrative Code
R2-7-704. Refusal to Submit Cost or Pricing Data A. If an offeror fails to submit cost or pricing data in the required form and within the time-frames required, the agency chief procurement officer may reject the offer. modifi- B. If a contractor fails to submit data to support a contract cation in the form required and within the time-frames required, the agency chief procurement officer may: 1. Reject the contract modification; or 2. Set the amount of the contract modification subject to the contractor’s rights under Article 9 of the Arizona Procurement Code. Historical Note New Section made by final rulemaking at 12 A.A.R. 508, effective April 8, 2006 (Supp. 06-1).