DHS OIG, OIG-12-05, U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative (2011)

DHS OIG

Section: U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative

Effective: 11/7/2011

Bluebook Citation: DHS OIG, OIG-12-05, U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative (2011)

Department of Homeland Security U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative OIG-12-05 November 2011 Office ofI//Spec/or General U.S. Department or Uomtland Security Washington. DC 20528 Homeland Security NOV 7 - 2011 Preface The Department of Homeland Security (DHS) Office of Inspector General (OIG) was established by the Homeland Security Act of2002 (Public Law 107-296) by amendment to the Inspector General Act of1978. This is one ofa series of audit, inspection, and special reports prepared as part of our oversight responsibilities to promote economy, efficiency, and effectiveness within the Department. This report addresses the effectiveness of the U.S. Customs and Border Protection's management of the purchase and storage of steel in support of the Secure Border Initiative.

It is based on interviews with employees and officials of relevant agencies and institutions, direct observations, and a review of applicable documents. The recommendations herein have been developed to the best knowledge available to our office, and have been discussed in draft with those responsible for implementation. We trust this report will result in more effective, efficient, and economical operations. We express our appreciation to all of those who contributed to the preparation of this report. ~;(~ Anne L. Richards Assistant Inspector General for Audits Table of Contents/Abbreviations Executive Summary .............................................................................................................1 Background ..........................................................................................................................2 Results of Audit ..................................................................................................................5 Project Planning .............................................................................................................5 Project Oversight ...........................................................................................................8 Conclusion ...................................................................................................................11 Recommendations........................................................................................................12 Management Comments and OIG Analysis ................................................................12 Appendices Appendix A: Purpose, Scope, and Methodology.......................................................15 Appendix B: Management Comments to the Draft Report .......................................16 Appendix C: Major Contributors to this Report ........................................................22 Appendix D: Report Distribution ..............................................................................23 Abbreviations U.S. Customs and Border Protection contracting officer Department of Homeland Security fiscal year International Boundary and Water Commission CBP CO DHS FY IBWC LOTSS Long-Term Steel Storage IIRIRA NFC OIG SBI SSCM TI Illegal Immigration Reform and Immigrant Responsibility Act of 1996 National Finance Center Office of Inspector General Secure Border Initiative Supply and Supply Chain Management Tactical Infrastructure OIG Department of Homeland Security Office of Inspector General Executive Summary The Department of Homeland Security’s Customs and Border Protection uses infrastructure to impede illegal entry into the United States and provide officers access to their areas of operations.

Since 2008, Customs and Border Protection has spent approximately $1.2 billion to construct physical barriers along the southwest border as part of the Department’s Secure Border Initiative. About $310 million of the cost was to purchase and store steel in support of fence construction. We performed this audit to determine the effectiveness of Customs and Border Protection’s management of the purchase and storage of steel in support of the Secure Border Initiative. Customs and Border Protection completed 299 miles of fence; however, it did not effectively manage the purchase and storage of steel in support of the Secure Border Initiative.

It purchased steel based on an estimate before legally acquiring land or meeting international treaty obligations. In addition, it did not provide effective contract oversight during the project: it paid invoices late, did not reconcile invoices to receiving documents, and did not perform a thorough review of the contractor’s selection of a higher-priced subcontractor or document the reasons for its approval of the subcontractor. As a result, Customs and Border Protection purchased more steel than needed, incurred additional storage costs, paid interest on late payments, and approved a higher-priced subcontractor, resulting in additional expenditures of about $69 million that could have been put to better use. We made five recommendations to improve Customs and Border Protection’s management of future fence construction and contract oversight.

Customs and Border Protection concurred with four recommendations, and the Department of Homeland Security proposed an alternative to the fifth recommendation that met the intent of that recommendation. Customs and Border Protection is taking action to implement the recommendations. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Background Achieving operational control of the U.S. border is one of the key missions of the Department of Homeland Security (DHS), and specifically U.S. Customs and Border Protection (CBP). CBP’s Border Patrol has 20 sectors responsible for detecting and preventing illegal entry of aliens into the United States between ports of entry.

Section 102 of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA) required the Attorney General to construct fencing and road improvements to prevent illegal entry at the border near San Diego, California.1 In November 2005, DHS established the Secure Border Initiative (SBI) to secure the Nation’s borders and reduce illegal immigration. DHS tasked CBP as the executive agent for the SBI program. CBP’s SBI Program Management Office was responsible for developing and constructing a comprehensive border protection system using a combination of technology, known as SBInet, and physical barriers, known as Tactical Infrastructure (TI). TI consists of roads, lighting, drainage improvements, bridges, and fencing to impede illegal entry into the United States and provide officers access to their areas of operations.

Congress amended Section 102(b) of the IIRIRA with the Secure Fence Act of 2006, requiring reinforced fence construction and accompanying physical barriers in priority areas along the southwest border in California, Texas, New Mexico, and Arizona. In September 2006, DHS awarded a 3­ year indefinite delivery/indefinite quantity contract to a prime contractor. The contractor was responsible for acquiring, deploying, and maintaining SBI technology while providing supply chain management for TI projects. The contractor was also responsible for selecting and managing a team of subcontractors to support the project.

In December 2007, the Consolidated Appropriations Act of 2008 further amended Section 102(b) of the IIRIRA to require DHS to construct not less than 700 miles of reinforced fencing along the southwest border “where fencing would be most practical and effective.” In carrying out that mandate, the Secretary was required to identify and build 370 miles “or other mileage” of priority fencing on the southwest border by December 31, 2008. In January 2008, CBP awarded the Supply and Supply Chain Management (SSCM) task order to a prime contractor for the purchase and storage of steel to support fence construction. The 1 The Homeland Security Act of 2002, as amended, transferred many authorities of the Attorney General to DHS. Section 564 of the Consolidated Appropriations Act of 2008, however, amended section 102 of the IIRIRA to replace “Attorney General, in consultation with the Commissioner of Immigration and Naturalization” with “Secretary of Homeland Security.” U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative SSCM task order consisted of three contracts for the purchase of steel, mesh, and storage.

Since fiscal year (FY) 2008, CBP has spent about $310 million to purchase and store steel in support of fence construction. During the performance of the SSCM task order, the contractor stored and distributed the steel from three locations: El Paso, Texas; Houston, Texas; and Lynwood, California. CBP consolidated the remaining steel at the end of the project to the El Paso, Texas, facility. Between the enactment of the Secure Fence Act of 2006 and the time of our review, CBP completed nearly 299 miles of fencing at a cost of $1.2 billion.2 To date, CBP has constructed about 650 miles of fencing along the southwest border, including the miles constructed using the steel from the SSCM task order.

Table 1 illustrates the fence miles from the SSCM task order and the total miles of fencing along the southwest border as of March 2011. Table 2 illustrates the total estimated cost for fence constructed under the SSCM task order. Figure 1 illustrates some of the pedestrian and vehicle fence designs. Table 1.

SSCM Task Order Miles and Total Miles Along the Southwest Border as of March 2011* Fence Type Pedestrian Vehicle Total Miles Built From SSCM Task Order 150.57 147.98 298.55 Total Miles of Fencing 351.79 298.85 650.64 * Figures include approximately 2.35 planned miles that were still under construction as of March 2011. 2 According to CBP, the cost per mile includes commercial construction, supply chain and planning oversight, environmental compliance and cultural mitigation, program management, design, and real estate planning and acquisition. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Table 2. Average Cost per Mile and Associated Totals of Fence Constructed Under the SSCM Task Order Fence Type Miles Built From SSCM Task Order Average Cost Per Mile Total Cost Pedestrian Vehicle Total 150.57 $6,500,000 147.98 $1,800,000 298.55 $978,705,000 $266,364,000 $1,245,069,000 Figure 1.

Examples of Southwest Border Fence Designs Pedestrian Fencing Images Courtesy of CBP Vehicle Fencing U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Results of Audit CBP did not effectively manage the steel and storage purchased under the SSCM task order. It purchased steel based on an estimate before legally acquiring land and meeting international treaty obligations. CBP did not provide effective contract oversight during the project, as demonstrated by paying invoices late and by not reconciling invoices to receiving documents. In addition, it did not perform a thorough review of the consent to subcontract and did not document the reasons for its approval of the higher-priced subcontractor.

As a result, CBP purchased more steel than needed, incurred additional storage costs, paid interest on late payments, and approved a higher-priced subcontractor. The insufficient planning and inadequate contract oversight led to additional expenditures of about $69 million that CBP could have put to better use. Project Planning CBP did not efficiently plan the purchase and storage of steel for the SSCM task order. It purchased steel based on an estimate of types of fence per mile.

As a result, 27,557 tons of extra steel, with a value of about $44 million, remained in storage at the end of the task order. Further, CBP incurred $9.8 million in additional storage costs because it did not move the remaining steel to a government facility for more than 2 years after the original storage contract expired. Steel Purchased for the SSCM Task Order CBP purchased steel based on an estimate of types of fence per mile. In March 2008, CBP instructed the prime contractor to purchase approximately 145,000 tons3 of steel before finalizing fence designs.

According to CBP, at that time it did not have access to all the land where it would build the fence and therefore could not properly plan the project or determine the appropriate fence design for all the planned miles. Because CBP did not have access to all the land, it based the initial purchase on an estimate completed in December 2007. CBP attributed the decision to purchase the steel in bulk to the December 31, 2008, deadline, an agreement with the supplier to purchase the steel at January 2008 prices, and production times for steel. Additionally, CBP did not obtain necessary approval to build all planned fence segments before acquiring the steel.

CBP was aware that it might be required to build new fence along the southwest border. To address this possibility, CBP performed multiple environmental assessments in areas where it might be required to build. In 2007, CBP performed an 3 According to CBP, the quantity of steel purchased included a 10% allowance for unanticipated design changes; it did not intend for the additional steel to be excess at the end of the contract. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Page 5 environmental assessment and determined that a permanent fence would result in adverse affects to the flood plain and recommended building a movable fence.

Despite this recommendation, the steel that CBP purchased was of a type to build a permanent fence. CBP purchased approximately 11,300 tons, or $20.5 million worth of steel to build 14 miles of permanent fence along the Rio Grande Valley. However, CBP did not meet the International Boundary Water Commission’s (IBWC) criteria for a fence type that would minimize effects of water flow on the flood plain. CBP consulted with the IBWC between 2008 and 2010 to find a solution to the impact on the flood plain.

The IBWC denied support of CBP’s proposal of permanent fence in this area because of the potential adverse impacts to the flood plain. According to CBP, it did not construct a movable fence in this area because of high cost. CBP indicated that the bulk purchase saved the government approximately $72 million based on the price per ton increase of raw steel from $550 in January 2008 to $1,060 in August 2008. Although the cost of raw steel did almost double in price, we were not able to validate CBP’s reported cost savings.

CBP computed the savings using raw steel prices rather than the manufactured purchase price. CBP paid $1,655 per ton for most (84%) of the steel rather than the $550 per ton used in its cost-savings analysis. In addition, CBP used the total amount of steel purchased (about 145,000 tons) in the calculation, instead of the amount needed (approximately 117,000 tons) to build about 299 miles of fence. Additional Purchase of Steel In September 2009, CBP purchased 34 tons of steel for $23,000, even though it had significant quantities of the same steel already in storage.

According to CBP, the subcontractor offered CBP the steel at a reduced price, and CBP determined that it would need it in the future. Table 3 illustrates the quantities in storage prior to the purchase of additional steel. Table 3. Breakdown of Additional Steel Purchase Length of Steel Purchase (Pieces) Weight (Tons) 21 foot 20 foot 25 foot Total 159 51 12 222 25 7 2 34 Pieces Already in Storage Weight (Tons) 24,142 35,033 12,090 71,265 3,683 5,091 2,196 10,970 U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Storage of Extra Steel CBP was not proactive and did not efficiently plan for the storage of steel remaining from the SSCM task order.

Instead of moving the extra steel to a cost-efficient location, CBP extended the original contract and awarded a supplemental storage contract. CBP’s decision to extend the storage contracts for 2 years resulted in $9.8 million in avoidable storage costs. The original storage contract for the SSCM task order covered the period from April to December 2008. During this period, CBP was aware that it would have at least 24,000 tons of remaining steel but did not begin to identify possible government-owned storage facilities until August 2009.

CBP made multiple revisions to the storage contract until it found a new storage site. The revisions extended the original storage contract 15 months, from January 2009 to March 2010, at a cost of about $5.6 million. In April 2010, CBP awarded a 1-year task order, Long-Term Steel Storage (LOTSS), under the SSCM task order for storing the steel through March 2011 for $4.1 million. A CBP legal review, cost/price, and technical evaluations of the LOTSS task order determined that the proposed amount for the LOTSS task order was unrealistically high and recommended that CBP include a memorandum in the contract file to explain why it accepted the cost/price proposal and the technical proposal.

However, CBP awarded the LOTSS task order for $4.1 million without including the memorandum or justifying the high cost. According to CBP, the legal review recommendation to justify the cost was only a suggestion and the contracting office chose not to accept it. In July 2010, almost 1 year after it began researching cost-effective storage locations, CBP identified a suitable site. In January 2011, CBP paid approximately $1 million to prepare the new site and estimated about $780,000 to transport the steel to the new facility.

At the time of our review, CBP was in the process of moving the remaining steel to the new site. Table 4 illustrates additional storage costs CBP incurred because of its delay in finding a cost-effective site. Table 4. Storage Costs Between January 2009 and March 2011 Task Order SSCM Task Order Revision (January 2009–June 2009) SSCM Task Order Revision (July 2009–December 2009) SSCM Task Order Extension (January 2010–March 2010) LOTSS Task Order (April 2010–March 2011) Total Amount $4,250,000 $908,385 $427,244 $4,167,381 $9,753,010 U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative CBP said that it will use the remaining steel to maintain and repair the existing fence and has already used some of it for these projects.

In January 2011, CBP transported approximately 500 tons of steel to two areas along the southwest border to replace damaged fencing. CBP also indicated that if required to build additional fence, it would use the extra steel for future construction projects. To ensure that future large-scale projects are as efficient as possible, CBP should analyze its performance under the SSCM task order and apply lessons learned to future projects. Project Oversight CBP did not provide effective oversight during the SSCM task order.

CBP increased the cost of the SSCM task order because it paid invoices late. In addition, it did not reconcile invoices and did not perform a thorough review of the consent to subcontract documentation. As a result, CBP incurred late payment interest charges and could not guarantee that the government received what it paid for under the task order. In addition, CBP approved a subcontractor that may have added about $13.5 million to the project.

Interest Payments CBP increased the cost of the SSCM task order because it paid invoices after the due date. The contractor submitted 28 invoices over the duration of the task order. Our review of the invoices showed that CBP paid 7 (25%) of 28 invoices late under the SSCM task order contract payment terms. Late payments occurred because CBP entered the contract into the system incorrectly, did not have policies in place for submitting and reviewing invoices, and did not establish a notification process to remind offices of an invoice coming due.

Additionally, CBP applied “net 21” as payment terms rather than the standard “net 30” terms. As a result, CBP paid approximately $282,000 of interest during the SSCM task order. Table 5 lists the seven invoices that accrued interest. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Table 5.

Contractor Invoices That Accrued Interest* Invoice 1 2 3 4 5 9 11** Total Payment Date Due Date (interest starts the day after) August 26, 2008 June 21, 2008 August 26, 2008 August 8, 2008 August 26, 2008 August 23, 2008 September 5, 2008 August 28, 2008 September 14, 2008 September 26, 2008 November 13, 2008 November 26, 2008 December 29, 2008 December 16, 2008 Days Late 65 17 2 7 11 12 12 Interest Paid $29,819 $44,915 $5,257 $61,718 $55,213 $48,241 $36,465 $281,628 *The National Finance Center (NFC) calculated the interest from the day after the due date through the payment date using rates of 4.75% (January 2008–June 2008) and 5.125% (July 2008–December 2008). The U.S. Department of the Treasury determined the applicable interest rates **CBP made two interest payments for invoice #11 for $36,465; one payment of $19,752 and the second payment was $16,713. Our review determined the second payment was a duplicate. CBP was aware of the duplicate payment and as of July 2011, it had not recovered the duplicate payment.

Without the duplicate payment, the total interest paid would have been about $265,000. CBP did not have policies and procedures for submitting and reviewing invoices. It also did not have clear guidance on the proper office to route invoices to, or timelines for the review process. In addition, CBP did not have a notification process to remind offices of an invoice coming due.

CBP applied accelerated payment terms to the SSCM task order. According to Title 5 of the Code of Federal Regulations §1315.14(c)(1)(iii) and CBP operating procedures, the standard payment terms for supplies and services are 30 days after receipt of an invoice, or “net 30.” However, CBP agreed to payment terms of 21 days after the receipt of an invoice, or “net 21.” According to CBP, the accelerated payment was an incentive for the contractor to produce expedited delivery schedules. However, as of April 2011, CBP personnel had not provided documents to support this statement. If CBP had applied the standard net 30 payment terms instead of net 21, it would have avoided approximately $178,000 (63%) of accrued interest payments.

Table 6 illustrates the amount of interest that CBP would have saved if it had applied the standard payment terms. In March 2009, after CBP paid 98% of the contract, it modified the contract to adjust the payment terms to net 30. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Table 6. Interest Savings Using the Standard Payment Terms Invoice Number 4 5 9 11 Total Interest Paid when Net 21 Terms Applied $61,718 $55,213 $48,241 $36,465 $201,637 Interest Paid if Net 30 Terms Applied Savings $0 $9,202 $10,338 $4,558 $24,098 $61,718 $46,011 $37,903 $31,907 $177,539 Invoice Reconciliation The Contracting Office did not reconcile invoices to receiving documentation.

The National Finance Center (NFC) is responsible for ensuring proper expenditure of appropriated funds for CBP. The invoice packet that the NFC received included a contracting officer’s (CO) technical representative acceptance letter and a contracting specialist’s checklist indicating approval for payment. The invoice packets did not contain supporting documentation for goods received. According to the Contracting Office, it relied on verbal confirmation from the program manager that the invoice amounts were accurate.

As a result, CBP cannot guarantee that the government received the accurate amount of steel for which it paid the contractor. Consent to Subcontract CBP did not perform a thorough review of the consent to subcontract documentation and did not document the reasons for its approval of the higher-price subcontractor. The Federal Acquisition Regulation states that if an approved purchasing system exists, COs may include a Consent to Subcontract clause in the contract if additional oversight is necessary because of the subcontract type, complexity, or value. The clause allows COs to determine whether contractors obtained adequate price competition and have a sound basis for deciding to select subcontractors.

Although the contractor had an approved purchasing system, CBP required the contractor to obtain its written consent for subcontracts under the SSCM task order. According to CBP, it intended to provide additional oversight of the selection of a subcontractor by participating, as a nonvoting member, in the contractor Source Selection Board meeting. CBP did not request documentation to support the contractor’s decision to select the higher- priced bidder. For example, the contractor’s price proposal showed an adjustment to the system-selected bidder by 5% to account for additional U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Page 10 transportation costs.

However, CBP did not request an explanation or review the adjustment. A review of supporting documentation would have determined that the contractor did not adequately document its decision to select the higher-priced bidder or justify the perceived benefits associated with the additional costs. It also would have determined that the contractor did not consistently follow the stated evaluation criteria in its request for proposals. Additionally, the consent to subcontract documentation did not show that the automated purchasing system selected a lower bidder as the recommended vendor, and the contractor did not document its reason for overriding the system’s selection.

CBP did not request documentation to support the contractor’s decision and did not justify the contractor’s selection. CBP’s lack of oversight may have increased the SSCM task order by the adjusted difference in bids of $13.5 million. Actions Taken by DHS DHS’s Office of the Chief Procurement Officer recognized the importance of component oversight of subcontractor selection and issued an acquisition alert in April 2011 to DHS heads of contracting activities. The purpose of the alert was to emphasize the responsibilities and considerations of a CO when evaluating prime contractors’ source selection decisions.

According to the alert, COs must review a contractor’s notification and supporting data to ensure that the proposed subcontract is appropriate for the risks involved and consistent with current policy and sound business judgment. At a minimum, the alert required COs to review all contractor requests for subcontract consent. These reviews must consider, among other things, whether the contractor performed adequate cost or price analysis or price comparisons. Conclusion CBP did not efficiently plan for the purchase and storage of steel in support of the SBI.

CBP purchased the steel based on an estimate before legally acquiring land or meeting international treaty obligations. In addition, CBP did not provide effective oversight during the project because it made late payments, did not reconcile invoices, and did not perform a thorough review of the consent to subcontract before approving the selected subcontractor. CBP needs to ensure that it applies lessons learned from the SBI project to future projects. The insufficient planning prior to the purchase of steel and the inadequate oversight of the SSCM led to the purchase of extra steel, additional storage costs, interest paid on late payments, and approval of a higher-priced subcontractor.

As a result, CBP spent about $69 million that it could have put to better use. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Recommendations We recommend that the Assistant Commissioner of the Office of Administration: Recommendation #1: Continue to relocate extra steel in storage to a more cost effective site. Recommendation #2: Perform a lessons learned analysis of the SSCM task order and apply the results to future projects. Recommendation #3: Develop and communicate policies and procedures for reconciling invoices.

Recommendation #4: Develop a reminder notification process to warn appropriate offices that invoices are due. Recommendation #5: Require contractors to inform the contracting officer if they override the automated purchasing system. Management Comments and OIG Analysis We obtained written comments on the draft report from CBP’s Assistant Commissioner, Office of Internal Affairs. We reviewed the comments and, where appropriate, made changes to the report.

According to its response to the draft report, CBP did not agree with the report’s conclusions. According to CBP, the report did not acknowledge the context in which CBP made many of its business decisions related to the purchase and storage of steel, contract oversight, and subcontractor selection. We recognize the constraints placed on CBP by The Secure Fence Act of 2006, but we maintain that if CBP had ensured that it legally acquired the land and met international treaty obligations before it purchased the steel, it would have reduced the cost to purchase and store the steel. CBP agreed that it made late payments, but stated that our finding did not reflect corrective actions it took before late payments became a systemic issue.

We recognize that there were no additional interest payments after invoice #11 related to the SSCM task order. However, CBP did not provide a copy of the corrective action plan it said it developed and implemented. OIG further maintains that the Contracting Office did not reconcile invoices to receiving documentation because the invoices it received did not contain sufficient detailed information to perform those reconciliations. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative We also recognize that CBP intended to provide additional oversight of the selection of a subcontractor by its appointment of a representative.

The CBP representative participated as a nonvoting member in the contractor Source Selection Board meeting but did not request documentation to support the contractor’s decision to select a higher- priced bidder. We believe that CBP needs to improve its processes and develop plans in anticipation of further construction of the fence along the border. We included a copy of the management comments in their entirety in appendix B. The following is an evaluation of CBP’s official response. Management Response on Recommendation #1 CBP concurred with the recommendation and stated that it relocated the remaining steel inventory to a government-owned site in Fabens, Texas, on March 31, 2011.

OIG Analysis: We consider CBP’s actions responsive and consider the recommendation resolved. However, it will remain open until CBP provides additional documentation. The DD 1149 CBP provided does not contain sufficient detail, and the additional inventory data did not account for the remaining steel. The recommendation will remain open until CBP provides a reconciled inventory of the remaining steel at the new government-owned site.

Management Response on Recommendation #2 CBP concurred with the recommendation. CBP’s Facilities Management & Engineering will coordinate with the U.S. Army Corps of Engineers and other internal stakeholders in a lessons learned session. The results of this session will include a lessons learned document that CBP will provide to OIG. OIG Analysis: We consider CBP’s actions responsive to the recommendation and consider the recommendation resolved.

However, it will remain open until CBP provides the lessons learned document. Management Response on Recommendation #3 CBP concurred with the recommendation and will develop and communicate policies and procedures for reconciling invoices. CBP’s Procurement Directorate is in the process of establishing and aligning invoice approval procedures based on lessons learned, a recent U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Page 13 reorganization, and the need to manage prescribed timelines to avoid late payment interest penalties. OIG Analysis: We consider CBP’s actions responsive to the recommendation and consider the recommendation resolved.

However, it will remain open until CBP provides invoice policies and procedures. Management Response on Recommendation #4 CBP concurred with the recommendation. CBP’s Financial Management Office will determine if its financial system can be programmed to send reminder notices regarding invoice payment due dates. If the system can be programmed to do so, CBP will include the notification process in the invoice procedures currently being developed.

OIG Analysis: We consider CBP’s actions responsive to the recommendation and consider the recommendation resolved. However, it will remain open until CBP provides documentation that a reminder notification process is in place, whether the financial system can be programmed or not. Management Response on Recommendation #5 CBP did not concur with the recommendation because it requires contractors to inform the CO if they override the automated purchasing system, which involves a change to the regulations. DHS proposed an alternative recommendation: Emphasize the importance of the contracting officer’s responsibility to adequately review a consent request and supporting data, including the contractor’s cost or price analysis of subcontracts.

OIG Analysis: Although CBP did not concur with the recommendation, DHS’s alternative recommendation meets the intent to provide additional oversight to ensure that government representatives mitigate risk to the government in the subcontractor selection process. We consider this recommendation resolved, but it will remain open until CBP provides documentation on the steps it is taking to implement the Department’s guidance on the importance of the CO’s responsibility. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix A Purpose, Scope and Methodology This report provides the results of our work to determine the effectiveness of CBP’s management and oversight over the purchase and storage of steel used for SBI. To achieve our objectives, we— Reviewed the contract documentation for the SSCM task order and the LOTSS task order applicable to the purchase and storage of steel; Interviewed CBP headquarters officials; CBP COs in Arlington, Virginia, regarding the steel purchase contract; CBP Budget Office officials in Indianapolis, Indiana; and Defense Contract Audit Agency and Defense Contract Management Agency officials in Huntsville, Alabama; Reviewed invoices that the contractor submitted to determine whether the invoices were complete and had accrued interest; Reviewed Environmental Impact Statements for areas where CBP planned to build TI; Reviewed CBP inventory records for the extra steel; Reviewed design changes related to the SSCM task order; Reviewed policies and procedures, including the Federal Acquisition Regulation, DHS Acquisition Manual, and CBP Directives; and Reviewed prior audit reports regarding SBI and TI.

We conducted this performance audit between October 2010 and April 2011 pursuant to the Inspector General Act of 1978, as amended, and according to generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based upon our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based upon our audit objectives. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report July 29, 2011 MEMORANDUM FOR CHARLES K..

EDWARDS ACIlNG DEPARTMEl'fT-OF HOMElAt'ID SECURITY INSPECfOR GENERAL FROM: SUBJECT: Assistant Office Qnnmissioner­ of Internal Affairs u.s. Customs and Border Protection's Response to the Office of Inspector General's Draft Report Entitled, "U.S. Customs and Border ProlCClion's of the Purchase and StorugeofSteel in Support oCthe Secure Management Border Initiative" . Thank you for the opportunity to review and offer commenls on the Department ofHomeland Security (DRS) Office of the Inspector General (OIG) draft report entitled ·'U.S. Customs and Border Protection's Management of the Purchase and Stomge ofStocl in Support of the Secme Border lnitiative," dated June 20, 2011. U.S. Customs and Border Protection (CDP) has reviewed the draft report and takes exception with several findings and conclusions in the report given they are nOI supported by program or procurement documentation. While we agree that the program incurred unanticipated costs, we markedlyOisagree with the amount of these costs and the reasons why they In short, ofthe $69 million questioned in the repol;1, we agree that approximately were incurred. $282,000 in unanticipated costs wen: attributable to cuors in wing CBP's accounting system 10 properly process invoices and track steel as an asset.

CBP immediately responded to these early challenges, c:orrecting them within 60 calendar days, resulting in DO late payments thet"c:after-. The balance ofthe costs discussed in the draft report WQ"C not program overruns. or funds spent unwisely as we briefly discussed here. 1be OIG made five recommendations in its draft report. CBP concun with Recommendations 1i1.1f2.

N3, and #4 and does DOt coocur with Reconuneodations #5. Pro1te! Planning In general., CBP wholly disagrees with the report's conclusion that $44 million in excess steel was purchased as a result of poor management practices. While CBP does continue to maintain an inventory ofstruetural stocl we find that the report fails to admowledge the context in which CBP made many ofits business decisions related to the purchase of stee~ for example: • The report fails to oonsider the constraints placed on the agency by the The Secure Fence Act 0[2006, as amended, that required CBP to deploy 670 miles oftaetical iofrastmcture within ani 8-month timeframe.

U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report 2 • • Prior to launching full scale procu.mnent and oonstruetioo activities CBP did, in fact, use ICS90TlS learned from initial small fr:ncc: construction projects to plan the full deployment. These early projects, like PF-70. demonstrated availability orand oompetilion for materials within the construction industry - including structural steel- that played a significant role in the successful, timely, and cost effective execution of the fence program. Project plllIlnins: was quite thorough in the context oflhc deadline for fence construction completion. Specifically, the "fence toolbox" which included detailed and tested fence designs was finalized and completed in December 2007 before steel was ordered.

This plWl.lling work provided a soWld estimating tool for detailing what CBP's steel requirements would be. • As one of the largest materiel requirements of the program, structural steel production and timely delivCl)' was critical to avoiding widespread oonstruction delays dming program Cltccution. 1bc time required for both fence construction and the receipt of manufactured steel materials required CBP to place its steel order in early in Fiscal Year (FY) 2008. Further, estimated savings of$72.4 million \VaS aclrieved by using this acquisition strategy. • 1be rem.aini..ng stnlCtUta1 steel not used for work-related to The Set:ure Fence Act is being used for maintenance and some new construction work.. The principal advantage to CBP bere is that the steel used for maintenance activities is the same production quality and has the same finish as currently installed fencing.

Further, the report also states that CBP proceeded with the ordering of steel prior to "obtaining necessary construction approval." However, as CBP's Office of Chief Counsel explained during the audit engagement, Pumulllt to Section 102(a) ofthe Illegalimmigration Reform and Immigrant Responsibility Act 0/1996, as originally enacted and as it currently reads, the Secretary of Homeland Security has long hlUl. the approval and authority from Congress to construct physical barriers and roads in the vicinity ofthe border in areas of high iUegal entry. Moreover, beginning in FY 2007, Congress began appropriating significant money to CBP, via the Border Security, Fencing, lnftastructure and Tcclmology (BSFIl) appropriation. for the construction oftactical infrastrucrure as well as the installation ofborder seauity technology. A3 such, CBP did in fact. possess the authority 10 constroct border fencing when the Supply and Supply Chain Management (SSCM) task order was awarded in January 2008. While the program did manage through several delays. they were related to the legal process for land acquisition, and ensuring that the United States complied with the requirements of certain treaties with Mexico and not poor program execution or planning.

Project Oversigbt CBP takes exception to the following statement used throughout the DIG report: "CBP did Dot provide effec1ive oversight." This statement is found in the Executive Summary, Results of Audit, Project Oversight and Conclusion sections of the DIG report. This statement as written in the report are based on OlG's findings: (1) that invoices were paid late; (2) nOI reconciling iovoices to receiving reports; and (3) not having visibility into the subcontractor selection process. First, CBP agrees that in fact late paymeots were made, bUI this finding does nOI reflc:et the fact thai com:ct:ive actions were taken before late payments became a systemic issue. CBP agrees that the program incurred unanticipated. costs; however, CBP disagrees with the causes oftbose costs as described in the draft report.

The unanticipated costs wct'c more ac:curatcly atmbuted to systemic U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report 3 errors and problems in implementing the payment system at the very beginning ofllie program. response to these early problems, the program developed and implemented an action plan and R:OOvc:n:d. There were 00 late paymCIllS afta anrccting the early acc:ounting and invoice problems. In Second, cap used extensive documentation to reconcile invoices. This documentarion consisted of SSCM Financial Status Report (Funds and Manhour Expenditure Report). Task Execution Plan (labor & materials); Ind Steel Mesh Weekly Status which were provided to OIG during the audit.

Third, CBP had extensive visibility into the contractor's subcontractor selection process. This subcontract was awarded with both CSP's concurrence and participation in the source selection process. The report inaccurately concludes that the selection of the subconuaetor led to additional costs (SI3.5M) over a lower price offeror. The subcontract was awarded as a ''best value" procurement and price alone was nollhe detc:nnining faacr. govemme:ot and contractor to use "best valuc" procedmes in determining award of contracts or suboontmcts when the situation wamnts as presmbed in FAR Part 15.100.

In addition, CBP disagrees with the implications that significant savinp aodIor cost avoidances would have been ac:bievcd by the selection ofme lowest bidder. The "best value" trade-off selection significantlyreduccd pc:rfonnance risk facing the program. The program managers were faced with the urgency to get the program started as soon as possible and the need to obtain large quantities of steel within significant time constraints. As a result, the selection of the subcontractor with a proven record to delivCl" the required large quantities of steel under tight time constraints was made in accordance to the "best value" criterion instead of a "lowest cosf'.

CBP considers that the contractor made a valid management decision. It is entirely appropriate for the With regard 10 "Consent to Subcontract," the DHS Office of the Chief Procurement Officer (OCPO) and CBP believe that this section, as currently written, is inaccurate and should either (8) be deleted in its entirety, or (b) be rewritten based on our collUI1ents that follow. The draft repon incorrectly asserts that CBP did not have visibility into the prime contractor's subcontractor selection process. The draft report furthc- inaccurately asserts thai the contractor did not notify CBP that it selected a vendor that was $13.5 million more than the vendor cboSOl by its automaled purchasing syslem.

However, supporting docwnents show that CBP was fully awan: oflhe initial price diffCl"eDCe ($29 million) at the time ofthe source selection decision as well as the difference after the transportation adjustment (S 13.5 million). 1be record shows that the CBP contraeting personnel were closely involved in the prime contractor's source selection process and were fully aware of the price differences. 1be CBP Supervisory Contract Specialist panicipated as a non-voting member in the Source Selection Board meeting where the source selection process was discussed in detail and the best value decision was made. The slide presentation of this meeting was submitted as part ofthe consent request.

In addition, CBP documented that it obtained and reviewed the source selection documents and approved the prime contractor's requcst for consent to subcontract,. as required under FAR 44.202. With regard to the contractor overriding their automated procurement system, our review found that due to technical limitations, the automated template could not effectively be used for determining the best value supplier for SSCM. For example, the template did not penni! input of sub-faClors used in the source seloetioD evaluation for SSCM. Thus, we believe that the override wasjUSlified­ therefore,. we recommend deleting this assertion from the final report.

U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report 4 However, we recognize that this subcontract review included some deficiencies. We believe the contractor failed to adequately document their source selection decision to select the higher-priced bidd«, includingjustifying the pereeived benefits associated with additional costs; and (2) the oonlrnetor, in its evaluation oCthe proposals, failed to consistently foUow the stated evaluation criteria in its request for proposal (RFP). We also accept that CBP should have performed a more oomplete review of the supporting data and documented the reasons for eBP's approval oftbe higher-price subcontractor. To correct this problem moving forward, the DHS OCPO issued an acquisition alert to all contracting personnel emphasizing the need to perfonn adequate subcontract reviews. as discussed in the paragraph that follows.

DHS's OCPO recognized the importance of component oversight ofsubcontractor selection and issued an acquisition alert in April 2011 to DHS heads of contracting activities. 1bc: purpose of the alert was to emphasize the responsibilities and considenttions of a CO when evaluating prime COnlmctors' source selection decisions. According to the alc:n,. COs must review a contnlClors DOtification and supporting data to ensure that the proposed subcontract is appropriate for the risks involved and oonsistC:llt with current policy and sound business judgmcot.

At a minimwn, the alert required COs to review all contractor requests for subcontract consent. These reviews must consider, among other things., whether the contrnctor peri"onned adequ.atc: cost or price analysis or price comparisons. lbis alert adequately addresses the deficiency found during the review. Conclusion and Recommendadons CBP believes that the report's conclusion should be rewriuen based on the general and detailed technical comments provided herein. Specifically, in thercport's conclusion, CBP recommends replacing "$69 million" with "$282,000" based solely on the payment of prompt payment interest.

The OIG's fivercoommendations and CBP's actions to address them are described below. Recommendation #1: Continue to relocate extra steel in storage to a more cost effective site. CBP Response: Coocur. CBP addressed this finding independently in March 2011.

CBP relocated the remaining stt:d inventory to a governroent-owned site in Fabens, Texas. This activity was completed on Man::h 31, 2011. Fonns Do..l 149, anached, substantiate completion of this action. CBP respectfully requests that the OIG close this recommendation.

Due Date: Complete. Recommendation #2: Perform a lcssowleamed analysis of the Supply and SupplyCbain Management task order and apply the results to future projects. CDP Response: Concur. CBP's Facilities Management & Engineering (FM&E) will engage in a lessons learned session that will include both internal stakeholders and representatives from the u.S. Army Corps of Engineers who were involved in the execution of the PF 225 and \IF 300 programs for which the steel was purchased.

The outputs ofthis lessons learned session will include a lessons leamed document that will be shared with the OIG to close this recommendation. Due Date: OCtober31,20l1 U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report 5 Rtglmmendation #3: Develop and communicate policies and procedures for reconciling invoices. CBP Response: Concur. CBP will develop and communicate policies and procedures for reconciling invoices.

CBP is in the proc:e:ss ofresolving a related recommendation foUDd in the GAO 11-68 "SECURE BORDER INITIATIVE: Controls Over Contractor Payments for the S8l Technology ComPODCDt Need Improvement" final report. The Procurement Direccorate is in the process of establishing and aligning invoice approval procedures based on "lessons learned," a recent reorganization, and the need to manage prescribed time lines to avoid laic payment interest pellalties. Also, CBP is improving the awareness afthe ris1:::s associated with the various contrac:l types through its DeW COTR Management Program. announced in April 2011, 10 Contracting Officers (COS) and Contracting Officer Technical Representatives (CQTRs). CBP has established an integrated project team (lP1) who arc currently drafting a directive to outline the invoice review and approval process, which will include identifying risk-based steps for various contract types.

The directive will also focus on timeliness ofinvoice receipt, review and proper handling through the payment process. The IPT is currently analyzing the invoice receipt through payment process. Upon determining the most effective process it will be included in the CBP directive. A CSP-wide communication plan will also be developed after the directive is approved and issued to ensure all CBP stakeholders and procurement penonnel Wldcrstand the invoice review and approval process.

Due Dlte: August 31, 2011 Recommendation #4: Develop a reminder notification process to warn appropriate offices that invoices are due. CBP Response: Concur. CBP iscurrcntly conrdinating with our Financial Management Office to dctcn:ninc if SAP, CBP's financial system, can be programmed to sc:od reminder notices 10 the appropriate personnc1 regarding the invoice payment due dates. This remi~notice will also be included in the directive if SAP has the capability.

Due Dlle: August 31, 2011 Recommendation #5: Require contractors to infonn the Contracting Officer if they override the automated purchasing system. eRP Response: Non-eoncur. DHS does not concur with this recommendation. This recommendation would require contractors to infonn the Contracting Officer if they override the automated p~asing system (this would involve a change to the regulations, which in turn would require following the regulatory process). As discussed above, we do not believe this was an issue in the subcontractor selection.

CBP was fully aware of the price differential and the contractor's rationale , for selecting the lrigher priced subcontractor. Thus, the deficiencies in the review of the subcontract did not have any material relationship to the contractor's decision to override the automated purchasing system. If a recommendation is included., we recommend it read as follows: Emphasize the importmrt:e o/the contrtu::ting ojJieer's responsibility to adeqUO/ely review a consent request and supporting data, including the conlTactor's C05t or price ana1~i.s 0/subcontracts. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix B Management Comments to the Draft Report Note that iftbe recommendation is rewritten as DHS leconnnends, lhen DHS will oon<:ur with the rec:ommmdatiOD (and has already implemented that reoommendatioa via oW" acquisition alen). •••••••••••••• With regard to the classification of the rqxn1, CBP has identified information within this report that warrants a "POI" Official Use Only" classification.

CBP's technical and sensitivity comments related to the infonnation included in the drafl.T~rtan; included in Attachment A. Once again. lhmk you for the opportunity to comment 00 the draft report. CBP looks forward to working with you on future homeland security engagements. If you have any questions regarding this response, please oontact me or have a member of your staff oontaa Ms. Lynn Richardson, CBP Audit Liaison, Office of Internal Affairs, at (202) 344·2953. Attaclunents: See Attachment A for teclmical comments and sensitivity review.

See Attachment B for procurement supporting documentation. See Attachment C for fence toolbox and 001149 supporting documentation. U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix C Major Contributors to this Report Linda Howard, Director Sean Pettersen, Audit Manager Lindsey Koch, Auditor-in-Charge Peter Christopher, Program Analyst Apostolos Exarchos, Program Analyst Thomas Hamlin, Program Analyst Edwin Soto, Program Analyst U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative Appendix D Report Distribution Department of Homeland Security Secretary Deputy Secretary Chief of Staff Deputy Chief of Staff General Counsel Executive Secretariat Director, GAO/OIG Liaison Office Assistant Secretary for Office of Policy Assistant Secretary for Office of Public Affairs Assistant Secretary for Office of Legislative Affairs CBP Audit Liaison Office of Management and Budget Chief, Homeland Security Branch DHS OIG Budget Examiner Congress Congressional Oversight and Appropriations Committees, as appropriate U.S. Customs and Border Protection’s Management of the Purchase and Storage of Steel in Support of the Secure Border Initiative ADDITIONAL INFORMATION AND COPIES To obtain additional copies of this report, please call the Office of Inspector General (OIG) at (202)254-4100, fax your request to (202)254-4305, e-mail your request to our OIG Office of Public Affairs at [email protected], or visit our OIG websites at www.dhs.gov/oig or www.oig.dhs.gov.

OIG HOTLINE

To report alleged fraud, waste, abuse or mismanagement, or any other kind of criminal or noncriminal misconduct relative to Department of Homeland Security programs and operations: • Call our Hotline at 1-800-323-8603 • Fax the complaint directly to us at (202)254-4292 • E-mail us at [email protected]; or • Write to us at: DHS Office of Inspector General/MAIL STOP 2600, Attention: Office of Investigation - Hotline, 245 Murray Drive SW, Building 410 Washington, DC 20528 The OIG seeks to protect the identity of each writer and caller.

Chat with this agency guidance using AI

Ask CiteLaw's AI Navigator anything about this agency guidance, verify citations, and research related authorities. Sign up for CiteLaw free today to get started.